Construction of ballastless track slabs completed for Indonesia's Jakarta-Bandung High-Speed Railway-Xinhua

Construction of ballastless track slabs completed for Indonesia's Jakarta-Bandung High-Speed Railway

Source: Xinhua

Editor: huaxia

2023-02-16 09:06:19

This aerial photo taken on Feb. 15, 2023 shows the construction site of the last ballastless track slab of Jakarta-Bandung High-Speed Railway in Karawang, West Java, Indonesia. (Xinhua/Xu Qin)

The total length of the ballastless track section is 85.3 km, accounting for 60 percent of the main line.

JAKARTA, Feb. 16 (Xinhua) -- The construction of ballastless track slabs along the whole line of Indonesia's Jakarta-Bandung High-Speed Railway (HSR) was completed on Wednesday.

The total length of the ballastless track section is 85.3 km, accounting for 60 percent of the main line, which is 142.3 km. Altogether 30,177 ballastless track slabs need to be laid, according to the railway operators.

The use of the new type of ballastless track slabs, which are featured with the advantages of a simple structure, stable performance and good durability, is based on the technology developed by China with complete intellectual property rights. It is a key element to ensure the smoothness and safety of the high-speed railway.

This aerial photo taken on Feb. 15, 2023 shows the construction site of the last ballastless track slab of Jakarta-Bandung High-Speed Railway in Karawang, West Java, Indonesia. (Xinhua/Xu Qin)

At present, all of the subgrade, bridge and station civil works have been completed. The railway is scheduled to start operation mid-year.

The high-speed line, a landmark project under the China-proposed Belt and Road Initiative, connects Indonesia's capital Jakarta and another major city Bandung.

With a design speed of 350 km per hour, the railway will cut the journey between Jakarta and Bandung from over three hours to around 40 minutes.