Aerial photo taken on May 25, 2022 shows the construction site of the last box girder on the box girder erection channel at the No. 4 casting yard in Bandung direction of Jakarta-Bandung High-Speed Railway, Indonesia.
All 343 box girders in Bandung direction of Indonesia's Jakarta-Bandung High-Speed Railway (HSR) were completed on Wednesday, a week ahead of schedule, which marks another major progress in the construction of the HSR. (Xinhua/Xu Qin)
JAKARTA, May 25 (Xinhua) -- All 343 box girders in Bandung direction of Indonesia's Jakarta-Bandung High-Speed Railway (HSR) were completed on Wednesday, a week ahead of schedule, which marks another major progress in the construction of the HSR.
The No. 4 casting yard of the Jakarta-Bandung HSR undertakes the prefabrication and erection of 1,007 box girders of the project, of which 343 girders are in Bandung direction.
The second branch of CREC Indonesia Jakarta-Bandung HSR Project Team, which undertook the task of erecting box girders in the direction of Bandung, has overcome the outbreak of the epidemic, the complex surrounding environment, and the safety risks of high-altitude operations.
At present, the project team is actively promoting the box girder erection work in the direction of Jakarta according to the overall arrangement of the construction.
With a design speed of 350 km per hour, the railway built with Chinese technology will cut the journey between Jakarta and Bandung, capital of West Java province, from more than three hours to around 40 minutes. ■
Photo taken on May 25, 2022 shows the construction site of the last box girder on the box girder erection channel at the No. 4 casting yard in Bandung direction of Jakarta-Bandung High-Speed Railway, Indonesia.
All 343 box girders in Bandung direction of Indonesia's Jakarta-Bandung High-Speed Railway (HSR) were completed on Wednesday, a week ahead of schedule, which marks another major progress in the construction of the HSR. (Xinhua/Xu Qin)
Aerial photo taken on May 25, 2022 shows the construction site of the last box girder on the box girder erection channel at the No. 4 casting yard in Bandung direction of Jakarta-Bandung High-Speed Railway, Indonesia.
All 343 box girders in Bandung direction of Indonesia's Jakarta-Bandung High-Speed Railway (HSR) were completed on Wednesday, a week ahead of schedule, which marks another major progress in the construction of the HSR. (Xinhua/Xu Qin)
Aerial photo taken on May 25, 2022 shows the construction site of the last box girder on the box girder erection channel at the No. 4 casting yard in Bandung direction of Jakarta-Bandung High-Speed Railway, Indonesia.
All 343 box girders in Bandung direction of Indonesia's Jakarta-Bandung High-Speed Railway (HSR) were completed on Wednesday, a week ahead of schedule, which marks another major progress in the construction of the HSR. (Xinhua/Xu Qin)
Aerial photo taken on May 25, 2022 shows the construction site of the last box girder on the box girder erection channel at the No. 4 casting yard in Bandung direction of Jakarta-Bandung High-Speed Railway, Indonesia.
All 343 box girders in Bandung direction of Indonesia's Jakarta-Bandung High-Speed Railway (HSR) were completed on Wednesday, a week ahead of schedule, which marks another major progress in the construction of the HSR. (Xinhua/Xu Qin)
Aerial photo taken on May 25, 2022 shows the construction site of the last box girder on the box girder erection channel at the No. 4 casting yard in Bandung direction of Jakarta-Bandung High-Speed Railway, Indonesia.
All 343 box girders in Bandung direction of Indonesia's Jakarta-Bandung High-Speed Railway (HSR) were completed on Wednesday, a week ahead of schedule, which marks another major progress in the construction of the HSR. (Xinhua/Xu Qin)